New lot-sizing formulations for less nervous production schedules

被引:30
作者
Kazan, O [1 ]
Nagi, R [1 ]
Rump, CM [1 ]
机构
[1] SUNY Buffalo, Dept Ind Engn, Buffalo, NY 14260 USA
关键词
production; inventory; lot sizing; material requirements planning; nervousness;
D O I
10.1016/S0305-0548(99)00076-3
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Previously scheduled production plans frequently need to be updated because of demand uncertainty. After making a comprehensive definition of nervousness which includes costs for changes in production schedule and quantity, we suggest three methodologies. Two methods are modified versions of very well-known methods: the Wagner-Whitin algorithm and the Silver-Meal heuristic. However, our definition of nervousness and its consequences for altering predetermined production volumes make the well-known property of producing either zero or a sum of several periods' demand suboptimal. Therefore a third method, a new mixed integer linear programming formulation, is proposed which is shown to be more effective in some cases. Numerical analyses are carried out for a wide range of possible cases, through which we provide insights to the most appropriate algorithm in a parameterized space.
引用
收藏
页码:1325 / 1345
页数:21
相关论文
共 17 条
[1]  
AULL RL, 1989, PRODUCTION INVENTORY, V30, P28
[2]  
Baker K.R., 1977, DECISION SCI, V8, P19, DOI [DOI 10.1111/J.1540-5915.1977.TB01065.X, 10.1111/j.1540-5915.1977.tb01065.x]
[3]   A COMPARISON OF STRATEGIES TO DAMPEN NERVOUSNESS IN MRP SYSTEMS [J].
BLACKBURN, JD ;
KROPP, DH ;
MILLEN, RA .
MANAGEMENT SCIENCE, 1986, 32 (04) :413-429
[4]   LESS NERVOUS MRP SYSTEMS - DYNAMIC ECONOMIC LOT-SIZING APPROACH [J].
CARLSON, RC ;
JUCKER, JV ;
KROPP, DH .
MANAGEMENT SCIENCE, 1979, 25 (08) :754-761
[5]  
De Bodt M. A., 1983, Decision Sciences, V14, P345, DOI 10.1111/j.1540-5915.1983.tb00190.x
[6]  
Federgruen A, 1996, NAV RES LOG, V43, P169, DOI 10.1002/(SICI)1520-6750(199603)43:2<169::AID-NAV2>3.0.CO
[7]  
2-8
[8]   MRP SYSTEMS UNDER SUPPLY AND PROCESS UNCERTAINTY IN AN INTEGRATED SHOP-FLOOR CONTROL ENVIRONMENT [J].
GUPTA, SM ;
BRENNAN, L .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1995, 33 (01) :205-220
[9]   An investigation of alternative dampening procedures to cope with MRP system nervousness [J].
Ho, CJ ;
Carter, PL .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1996, 34 (01) :137-156
[10]  
Kropp D. H., 1983, Decision Sciences, V14, P156, DOI 10.1111/j.1540-5915.1983.tb00177.x