Shielding production: Essential step in production control

被引:190
作者
Ballard, G [1 ]
Howell, G [1 ]
机构
[1] Univ Calif Berkeley, Oakland, CA 94619 USA
来源
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE | 1998年 / 124卷 / 01期
关键词
D O I
10.1061/(ASCE)0733-9364(1998)124:1(11)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Effective production control systems are structured around the assignment as the unit of analysis. The quality of work assignments in production units such as construction crews and engineering squads is the key to production control and for determining production unit productivity. Research has revealed that the quality of assignments can be substantially improved by forming and selecting them to meet soundness, sequence, and size criteria. Quality assignments shield production units from work flow uncertainty, enabling those units to improve their own productivity, and also improve the productivity of the production units downstream. The associated reduction in task duration can shorten projects. Further reduction of project duration comes from shortening the buffers previously needed to accommodate flow uncertainty.
引用
收藏
页码:11 / 17
页数:7
相关论文
共 15 条
[1]  
[Anonymous], CONSTRUCTION PROJECT
[2]  
Ballard G., 1997, LEAN CONSTRUCTION
[3]  
BALLARD G, 1994, P C COMP CIV ENG ASC
[4]  
BALLARD G, 1996, P 4 ANN C LEAN CONST
[5]  
Bertrand J., 1990, PRODUCTION CONTROL S
[6]  
CRUZ JC, 1996, THESIS CATOLICA U CH
[7]  
HOUVILA P, 1997, LEAN CONSTRUCTION
[8]  
HOWELL G, 1995, IMPROVING PERFORMANC
[9]  
HOWELL G, 1995, MANAGING UNCERTAINTY
[10]   DEVELOPMENT OF A REGULATORY FRAMEWORK FOR THE USE OF UNDERGROUND SPACE IN HONG-KONG [J].
HOWELLS, DJ ;
CHAN, TCF .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 1993, 8 (01) :37-40