DEVELOPMENT OF A STOCHASTIC-MODEL FOR THE ECONOMIC-DISPATCH OF ELECTRIC-POWER

被引:28
作者
BUNN, DW [1 ]
PASCHENTIS, SN [1 ]
机构
[1] ORCO LTD ATHENS,ATHENS,GREECE
关键词
ELECTRIC POWER SYSTEMS - Load Dispatching - ELECTRIC UTILITIES - Economics - MATHEMATICAL PROGRAMMING; LINEAR;
D O I
10.1016/0377-2217(86)90059-7
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A large-scale model to support the online scheduling of power generation at 5 minute intervals is developed using a form of stochastic linear programming. This model takes explicit account of the expected recourse action which will be associated with the mismatch between dispatched generation and actual load demanded. Various experimental results on data for the S. W. Region of the CEGB demonstrate the economic efficiency of this approach over the more conventional deterministic linear programming model.
引用
收藏
页码:179 / 191
页数:13
相关论文
共 26 条
[1]  
ALDER RB, 1978, WIN P IEEE PES M NEW
[2]  
[Anonymous], 1980, STOCHASTIC PROGRAMMI
[3]  
BLOOM J, 1977, OR06477 MIT OP RES C
[4]   A MODEL-SWITCHING CRITERION FOR A CLASS OF STOCHASTIC LINEAR-PROGRAMS [J].
BUNN, DW ;
PASCHENTIS, SN .
APPLIED MATHEMATICAL MODELLING, 1981, 5 (05) :336-340
[5]  
BUNN DW, 1983, ENERGY MODELS STUDIE, P399
[6]   LINEAR PROGRAMMING UNDER UNCERTAINTY [J].
Dantzig, George B. .
MANAGEMENT SCIENCE, 1955, 1 (3-4) :197-206
[7]   INTEGER PROGRAMMING APPROACH TO THE PROBLEM OF OPTIMAL UNIT COMMITMENT WITH PROBABILISTIC RESERVE DETERMINATION [J].
DILLON, TS ;
EDWIN, KW ;
KOCHS, HD ;
TAUD, RJ .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1978, 97 (06) :2154-2166
[8]  
EDWIN KW, 1980, P IEE C POWER SYSTEM, P132
[9]   ECONOMIC AND OPERATIONAL IMPLICATIONS OF A COMPLEX OF WIND-DRIVEN GENERATORS ON A POWER SYSTEM [J].
FARMER, ED ;
NEWMAN, VG ;
ASHMOLE, PH .
IEE PROCEEDINGS-A-SCIENCE MEASUREMENT AND TECHNOLOGY, 1980, 127 (05) :289-295
[10]  
FARMER ED, 1980, P IEE C POWER SYSTEM, P125