A HYBRID APPROACH TO SEQUENCING JOBS USING HEURISTIC RULES AND NEURAL NETWORKS

被引:35
作者
KIM, SY
LEE, YH
AGNIHOTRI, D
机构
[1] SAMSUNG ELECTR CO,DIV SEMICOND,KIHUNG,SOUTH KOREA
[2] RUTGERS STATE UNIV,GRAD SCH MANAGEMENT,PISCATAWAY,NJ 08855
[3] RUTGERS STATE UNIV,DEPT IE,PISCATAWAY,NJ 08855
关键词
JOB SEQUENCING; SINGLE-MACHINE WEIGHTED TARDINESS PROBLEM; HEURISTIC RULES; NEURAL NETWORKS;
D O I
10.1080/09537289508930302
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
A hybrid approach to solve job sequencing problems using heuristic rules and artificial neural networks is proposed. The problem is to find a job sequence for a single machine that minimizes the total weighted tardiness of the jobs. Two different cases are considered: (1) when there are no setups, and (2) when there are sequence-dependent setup times. So far, successful heuristic rules for these cases are: apparent tardiness cost (ATC) rule proposed by Vepsalainen and Morton for the former case, and an extended version of the ATC rule (ATCS) proposed by Lee, Bhaskaran, and Pinedo for the latter. Both approaches utilize some look-ahead parameters for calculating the priority index of each job. As reported by Bhaskaran and Pinedo, the proper value of the look-ahead parameter depends upon certain problem characteristics, such as due-date tightness and due-date range. Thus, an obvious extension of the ATC or the ATCS rule is to adjust the parameter values depending upon the problem characteristics: this is known to be a difficult task. In this paper, we propose an application of a neural network as a tool to 'predict' proper values of the look-ahead parameters. Our computational tests show that the proposed hybrid approach outperforms both the ATC rule with a fixed parameter value and the ATCS using the heuristic curve-fitting method.
引用
收藏
页码:445 / 454
页数:10
相关论文
共 25 条
[11]  
FOO YPS, 1988, P IEEE ICNN, V2
[12]  
HOPFIELD JJ, 1985, BIOL CYBERN, V52, P141
[13]   NEURAL NETWORKS AND PHYSICAL SYSTEMS WITH EMERGENT COLLECTIVE COMPUTATIONAL ABILITIES [J].
HOPFIELD, JJ .
PROCEEDINGS OF THE NATIONAL ACADEMY OF SCIENCES OF THE UNITED STATES OF AMERICA-BIOLOGICAL SCIENCES, 1982, 79 (08) :2554-2558
[14]  
LAWLER EL, 1978, ANN DISCRETE MATH, V1, P331
[15]  
LEE YH, 1992, HEURISTIC MINIMIZE T
[16]  
LIPPMANN RP, 1987, IEEE ASSP MAGAZI APR
[17]  
PINEDO M, 1991, SCHEDULING HDB IND E
[18]   SINGLE-MACHINE TARDINESS SEQUENCING HEURISTICS [J].
POTTS, CN ;
VANWASSENHOVE, LN .
IIE TRANSACTIONS, 1991, 23 (04) :346-354
[19]   A NOTE ON THE WEIGHTED TARDINESS PROBLEM [J].
RACHAMADUGU, RMV .
OPERATIONS RESEARCH, 1987, 35 (03) :450-452
[20]   REAL-TIME SCHEDULING OF AN AUTOMATED MANUFACTURING CENTER [J].
RAMAN, N ;
RACHAMADUGU, RV ;
TALBOT, FB .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1989, 40 (02) :222-242