Single-machine group scheduling with a time-dependent learning effect

被引:93
作者
Kuo, WH
Yang, DL [1 ]
机构
[1] Natl Formosa Univ, Dept Informat Management, Tenri, Nara 632, Japan
[2] Da Yeh Univ, Dept Ind Engn & Technol Management, Changhua 515, Taiwan
[3] Natl Formosa Univ, Dept Informat Management, Yunlin 632, Taiwan
关键词
group scheduling; time-dependent; learning effect;
D O I
10.1016/j.cor.2004.11.024
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In many realistic situations, the more time you practice, the better learning effect you obtain. Thus, we propose a time-dependent learning effect and introduce it into the single-machine group scheduling problems. The two objectives of scheduling problems are to minimize the makespan and the total completion time, respectively. We also provide two polynomial time algorithms to solve these problems. (c) 2004 Elsevier Ltd. All rights reserved.
引用
收藏
页码:2099 / 2112
页数:14
相关论文
共 13 条
[1]   SCHEDULING GROUPS OF JOBS IN THE 2-MACHINE FLOW-SHOP [J].
BAKER, KR .
MATHEMATICAL AND COMPUTER MODELLING, 1990, 13 (03) :29-36
[2]   Single-machine scheduling with learning considerations [J].
Biskup, D .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 115 (01) :173-178
[3]  
HAM I, 1985, GROUP TECHNOLOGY APP, P100
[4]   A bi-criterion single-machine scheduling problem with learning considerations [J].
Lee, WC ;
Wu, CC ;
Sung, HJ .
ACTA INFORMATICA, 2004, 40 (04) :303-315
[5]   Minimizing total completion time in a two-machine flowshop with a learning effect [J].
Lee, WC ;
Wu, CC .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2004, 88 (01) :85-93
[6]   Parallel machine scheduling with a learning effect [J].
Mosheiov, G .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2001, 52 (10) :1165-1169
[7]   Scheduling with general job-dependent learning curves [J].
Mosheiov, G ;
Sidney, JB .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 147 (03) :665-670
[8]   Scheduling problems with a learning effect [J].
Mosheiov, G .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2001, 132 (03) :687-693
[9]  
Nadler G., 1963, INT J PROD RES, V2, P115, DOI DOI 10.1080/00207546308947818
[10]   2-MACHINE AND 3-MACHINE FLOW-SHOP SCHEDULING PROBLEMS WITH EQUAL SIZED TRANSFER BATCHES [J].
VICKSON, RG ;
ALFREDSSON, BE .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1992, 30 (07) :1551-1574