Effective scheduling of a large-scale paint production system

被引:25
作者
Adonyi, Robert [1 ]
Biros, Gabor [1 ]
Holczinger, Tibor [1 ]
Friedler, Ferenc [1 ]
机构
[1] Univ Pannonia, Dept Comp Sci, H-8200 Veszprem, Hungary
关键词
Paint production; Batch process scheduling; S-graph; Waste minimization;
D O I
10.1016/j.jclepro.2006.08.021
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Due to the large variety of options offered to customers, batch production schemes are highly accepted in the paint industry implying that scheduling plays an important role in optimal allocation of plant resources among multiple products. Since in a batch process, the cleaning of equipment units is the major source of waste, waste minimization is also to be taken into account in determining the schedule. The formerly developed S-graph framework [Sanmarti E, Holczinger T, Puigjaner L, Friedler F. Combinatorial framework for effective scheduling of multipurpose batch plants. AIChE Journal 2002;48(11):2557-70.] proved to be highly effective in solving multipurpose batch scheduling; it has now been specialized for solving paint production scheduling problems including waste minimization. The efficacy of the new approach is illustrated with the solution of large-scale paint production scheduling problems. (C) 2006 Elsevier Ltd. All rights reserved.
引用
收藏
页码:225 / 232
页数:8
相关论文
共 15 条
[1]   An MILP Continuous-Time Framework for Short-Term Scheduling of Multipurpose Batch Processes Under Different Operation Strategies [J].
Alberto Mendez, Carlos ;
Cerda, Jaime .
OPTIMIZATION AND ENGINEERING, 2003, 4 (1-2) :7-22
[2]   Heuristic algorithms for scheduling an automated wet-etch station [J].
Bhushan, S ;
Karimi, IA .
COMPUTERS & CHEMICAL ENGINEERING, 2004, 28 (03) :363-379
[3]   Makespan minimization for chemical batch processes using non-uniform time grids [J].
Burkard, RE ;
Fortuna, T ;
Hurkens, CAJ .
COMPUTERS & CHEMICAL ENGINEERING, 2002, 26 (09) :1321-1332
[4]  
Holczinger T., 2002, HUNGARIAN J IND CHEM, V30, P305
[5]   A GENERAL ALGORITHM FOR SHORT-TERM SCHEDULING OF BATCH-OPERATIONS .1. MILP FORMULATION [J].
KONDILI, E ;
PANTELIDES, CC ;
SARGENT, RWH .
COMPUTERS & CHEMICAL ENGINEERING, 1993, 17 (02) :211-227
[6]   An effective technique for wastewater minimisation in batch processes [J].
Majozi, T .
JOURNAL OF CLEANER PRODUCTION, 2005, 13 (15) :1374-1380
[7]   Optimal cleaning schedule for heat exchangers in a heat exchanger network [J].
Markowski, M ;
Urbaniec, K .
APPLIED THERMAL ENGINEERING, 2005, 25 (07) :1019-1032
[8]   An MILP continuous-time approach to short-term scheduling of resource-constrained multistage flowshop batch facilities [J].
Méndez, CA ;
Henning, GP ;
Cerdá, J .
COMPUTERS & CHEMICAL ENGINEERING, 2001, 25 (4-6) :701-711
[9]   Continuous time representation approach to batch and continuous process scheduling. 1. MINLP formulation [J].
Mockus, L ;
Reklaitis, GV .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 1999, 38 (01) :197-203
[10]  
Orcun S, 1997, COMPUT CHEM ENG, V21, pS673