U-shaped production lines: A review of theory and practice

被引:112
作者
Miltenburg, J [1 ]
机构
[1] McMaster Univ, Michael DeGroote Sch Business, Hamilton, ON L8S 4M4, Canada
基金
加拿大自然科学与工程研究理事会;
关键词
production lines; just-in-time; cellular manufacturing;
D O I
10.1016/S0925-5273(00)00064-5
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Most writers describe the U-shaped production line as the special type of cellular manufacturing used in just-in-time (JIT) production systems. JIT is defined to be an umbrella term for a number of techniques whose purpose is to improve product quality and cost by eliminating all waste in the production system. The U-line arranges machines around a U-shaped line in the order in which production operations are performed. Operators work inside the IJ-line. One operator supervises both the entrance and the exit of the line, machine-work is separated from operator-work so that machines work independently as much as possible. Standard operation charts specify exactly how all work is done. U-lines may be simple or complex. U-lines are rebalanced periodically when production requirements change. The U-line satisfies the flow manufacturing principle. This requires operators to be multi-skilled to operate several different machines or processes. It also requires operators to work standing up and walking. When setup times are negligible, U-lines are operated as mixed-model lines where each station is able to produce any product in any cycle. When setup times are larger, multiple U-lines are formed and dedicated to different products. 114 US and Japanese U-lines are examined in this study. The average U-line has 10.2 machines and 3.4 operators. About one-quarter of all U-lines are manned by one operator and so run in chase mode. The reported benefits are impressive. Productivity improved by an average of 76%. WIP dropped by 86%. Leadtime shrunk by 75%. Defective rates dropped by 83%. (C) 2001 Elsevier Science B.V. All rights reserved.
引用
收藏
页码:201 / 214
页数:14
相关论文
共 44 条
[11]  
DUTTON B, 1989, MANUFACTURING SYSTEM, V7, P38
[12]  
EDWARDS JN, 1993, TARGET PERIODICAL AS, V9, P5
[13]  
FORD S, 1997, TARGET PERIODICAL AS, V13, P53
[14]  
GRYA J, 1995, MAT HANDLING ENG, V50, P34
[15]  
Hall, 1983, ZERO INVENTORIES
[16]   CYCLIC SCHEDULING FOR IMPROVEMENT [J].
HALL, RW .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1988, 26 (03) :457-472
[17]  
Hirano H., 1988, JIT FACTORY REVOLUTI
[18]  
*JAP MAN ASS, 1985, JUST IN TIM TOYOT
[19]   THE U-LINE LINE BALANCING PROBLEM [J].
MILTENBURG, GJ ;
WIJNGAARD, J .
MANAGEMENT SCIENCE, 1994, 40 (10) :1378-1388
[20]   Balancing U-lines in a multiple U-line facility [J].
Miltenburg, J .