A multi-criteria adaptive control scheme based on neural networks and fuzzy inference for DRC manufacturing systems

被引:27
作者
Araz, Oezlem Uzun [1 ]
Salum, Latif [1 ]
机构
[1] Dokuz Eylul Univ, Dept Ind Engn, Izmir, Turkey
关键词
dual resource constrained (DRC) systems; real-time scheduling; multi-criteria scheduling; artificial neural network; fuzzy inference; CONSTRAINED JOB SHOPS; DISPATCHING RULES; ASSIGNMENT POLICIES; DYNAMIC SELECTION; SIMULATION; FLEXIBILITY; SCHEDULER; CRITERIA;
D O I
10.1080/00207540802471256
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Manufacturing systems are uncertain and dynamic systems, hence, they require real-time scheduling to adapt to changing manufacturing conditions. Current real-time scheduling approaches have been devised mainly for machine-only constrained systems, in which the shop capacity is constrained only by machine capacity, rather than for dual resource constrained (DRC) systems, in which the shop capacity is constrained by machine and worker capacity. In particular, there is no study on DRC system scheduling in which the 'where' and 'when' worker assignment rules, basic features of DRC systems, are altered in real-time (dynamically selected) to respond to new manufacturing conditions. Besides, multi-criteria DRC system scheduling has not yet been addressed extensively. Also, there has been little research on the interactions of dynamically selected job dispatching, worker assignment and job routing rules, which have a significant impact on DRC system performance. This paper proposes a multi-criteria real-time scheduling methodology for DRC systems to address these issues, and investigates these interactions. The methodology employs artificial neural networks as meta-models to reduce computational complexity and a fuzzy inference system to cope with multiple performance criteria. Various simulation experiments demonstrate that the methodology provides satisfactory results for real-time DRC systems scheduling.
引用
收藏
页码:251 / 270
页数:20
相关论文
共 58 条
[31]   A SOLUTION TO THE MULTIPLE SET-UP PROBLEM WITH DYNAMIC DEMAND [J].
LEE, CY .
IIE TRANSACTIONS, 1989, 21 (03) :266-270
[32]   Using Functional Virtual Population as assistance to learn scheduling knowledge in dynamic manufacturing environments [J].
Li, DC ;
Chen, LS ;
Lin, YS .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2003, 41 (17) :4011-4024
[33]   A case study in a dual resource constrained job shop [J].
Liao, CJ ;
Lin, HT .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1998, 36 (11) :3095-3111
[34]  
Lippmann R. P., 1988, Computer Architecture News, V16, P7, DOI [10.1109/MASSP.1987.1165576, 10.1145/44571.44572]
[35]   AN EVALUATION OF WORKER ASSIGNMENT POLICIES IN DUAL RESOURCE-CONSTRAINED JOB SHOPS WITH HETEROGENEOUS RESOURCES AND WORKER TRANSFER DELAYS [J].
MALHOTRA, MK ;
KHER, HV .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1994, 32 (05) :1087-1103
[36]   EXPERIMENT IN LINGUISTIC SYNTHESIS WITH A FUZZY LOGIC CONTROLLER [J].
MAMDANI, EH ;
ASSILIAN, S .
INTERNATIONAL JOURNAL OF MAN-MACHINE STUDIES, 1975, 7 (01) :1-13
[37]   A competitive neural network approach to multi-objective FMS scheduling [J].
Min, HS ;
Yih, Y ;
Kim, CO .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1998, 36 (07) :1749-1765
[38]   Development of a real-time multi-objective scheduler for a semiconductor fabrication system [J].
Min, HS ;
Yih, Y .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2003, 41 (10) :2345-2364
[39]  
Montgomery D.C., 2001, Design and Analysis of Experiments
[40]  
OUELHADJ D, 2007, J SCHEDULIN IN PRESS