Finance-based scheduling: Tool to maximize project profit using improved genetic algorithms

被引:77
作者
Elazouni, AM
Metwally, FG
机构
[1] King Fahd Univ Petr & Minerals, Dept Construct Engn & Management, Dhahran 31261, Saudi Arabia
[2] Zagazig Univ, Fac Engn, Zagazig, Egypt
关键词
D O I
10.1061/(ASCE)0733-9364(2005)131:4(400)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Contractor's ability to procure cash to carry out construction operations represents a crucial factor to run profitable business. Bank overdrafts have always been the major source to finance construction projects. However, it is not uncommon that bankers set a limit on the credit allocated to an established overdraft. Bankers' interest rates and consequently contractors' financing costs are basically determined based on the allocated credit limits. Furthermore, project indirect costs are directly proportional to the project duration which is affected by the allocated credit limit. Thus, the credit limit affects project financing costs and indirect costs which in turn affect project profit. However, finance-based scheduling produces financially executable schedules at specified credit limits while maintaining the demand of time minimization. Thus, finance-based scheduling provides a tool to control the credit requirements. This control enables contractors to negotiate lower interest rates which reduce financing costs. Thus, finance-based scheduling enables contractors to reduce project indirect costs and financing costs. This paper utilizes genetic algorithm's technique to devise finance-based schedules that maximize project profit through minimizing financing costs and indirect costs.
引用
收藏
页码:400 / 412
页数:13
相关论文
共 12 条
[1]   PROFIT MEASURES FOR CONSTRUCTION PROJECTS [J].
AU, T ;
HENDRICKSON, C .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (02) :273-286
[2]   Construction resource scheduling with genetic algorithms [J].
Chan, WT ;
Chua, DKH ;
Kannan, G .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (02) :125-132
[3]  
CHENG Y, 1993, QSB QUANTITATIVE SYS
[4]   Finance-based scheduling of construction projects using integer programming [J].
Elazouni, AM ;
Gab-Allah, AA .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2004, 130 (01) :15-24
[5]   Using genetic algorithms to solve construction time-cost trade-off problems [J].
Feng, CW ;
Liu, LA ;
Burns, SA .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) :184-189
[6]   Genetic algorithms application and testing for equipment selection [J].
Haidar, A ;
Naoum, S ;
Howes, R ;
Tah, J .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1999, 125 (01) :32-38
[7]   Optimization of resource allocation and leveling using genetic algorithms [J].
Hegazy, T .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1999, 125 (03) :167-175
[8]   GA-based multicriteria optimal model for construction scheduling [J].
Leu, SS ;
Yang, CH .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1999, 125 (06) :420-427
[9]   Site-level facilities layout using genetic algorithms [J].
Li, H ;
Love, PED .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1998, 12 (04) :227-231
[10]   Using machine learning and GA to solve time-cost trade-off problems [J].
Li, H ;
Cao, JN ;
Love, PED .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 1999, 125 (05) :347-353